Labor Day
==============================
No matter how many surveyors are employed by me and how many engineers I have to have the following
for a survey crew and engineer.
Capital needs for additional workers.
Survey crew:
GPS / Total Station $ 25 K
Beat Up Work Truck $ 20 K
Equipment ( Bush hooks, plumb bombs, reflectors, 2 lb sledge hammer, nails, No. rebar for setting corners,
Plastic Caps with my name for setting on the end the rebars and other misc crap they have to have)
Equipment $ 5 K
So 50 K for me to run a survey crew.
Where is that 50 K coming from, are the surveyors throwing 50K into the pot when hired or bring this
Now Engineers:
Computer $ 3 K
Autocad with Civil 3D $ 2.8 K
So when I hire and engineer are they throwing 5.8 K into the pot or bring it with them?
Also someone must get the additional work for these guys, who is doing that?
Them or me?